BIDDING & PROCUREMENT
CURRENT BIDS/RFQ'S
Requests for Proposals/Qualifications
City of Homewood Fire Station #2
Click HERE for a copy of the full RFP
The City of Homewood (City) is soliciting qualifications from Architectural & Engineering firms (or teams)
to provide professional design, bid and construction documents, and contract administration services
for a new fire station. This will be a qualifications-based selection process. Firms with relevant
experience in designing fire stations or combined public safety buildings that house fire services, and the
qualifications to perform the services outlined herein, are encouraged to respond. Firms may partner
with other firms to ensure that the design team provides the appropriate level of expertise in the
required disciplines. However, design teams must designate one lead firm. The lead firm shall be
responsible for meeting all the requirements of the proposal.
The purpose of the RFQ process is to identify the firm which the City determines is best suited to
support the City in this important project. Following an analysis of the responses to this RFQ, firm(s) may
be invited for interviews, with one firm being selected for further negotiation. The firm ultimately
awarded a contract by the City will provide services directed by the City of Homewood.
All questions concerning this RFQ shall be directed, in writing, to:
Cale Smith, PE, City Engineer
City of Homewood
2850 19th Street South
Homewood, AL 35209
Questions shall be submitted at least five (5) business days before the response deadline. Questions
received after this time will not be addressed. Responses from the City that substantially alter this
RFQ will be issued in the form of a written addendum and posted on the City’s website. All
proposals submitted shall remain open to acceptance for ninety (90) days from the response
deadline.
May 13, 2025 - Response deadline for A/E Firms
May 14-20, 2025 - Homewood Selection Committee Evaluation 1
May 22, 2025 - Notification to the top ranked A/E firms
July 10, 2025 - Homewood oral interviews (top ranked A/E firms)
July 14, 2025 - City Council Referral Agenda for Recommendation
June 28, 2025 - A/E approval by Homewood City Council
Requests for Proposals/Qualifications
City of Homewood Comprehensive Plan RFP
Click HERE for a copy of the full RFP
The Regional Planning Commission of Greater Birmingham (RPCGB) is seeking proposals from qualified consulting firms (or teams of firms) to develop a new citywide Comprehensive Plan for the City of Homewood in Jefferson County, Alabama.
As the city’s form of government moves to a Council-Manager form, an updated vision for the City will be important to guide this transition, as well as to inform capital improvement investments, gaps in public services and future land use decisions. The last Homewood Master Plan was adopted in 2007. Since then, the City has grown from 25,000 people in 2007 to approximately 28,000 people.
Anticipated compensation for the project is between $300,000 - $350,000 for the consultant team. Please note that a cost proposal is not a required element of this RFP. The project fee will be negotiated with the consulting firm / team that is selected.
The project is anticipated to be developed over an 18-month period after the Notice to Proceed is issued in November 2025.
RFP Issue Date: Monday, April 14, 2025
Questions Due: Monday, April 21, 2025 by 5 PM (CST)
Answers to Questions posted: Monday, April 28, 2025 by 5 PM (CST)
Proposals Due: Wednesday, May 14, 2025 by 5 PM (CST)
Notice of Short Listing: Wednesday, June 4, 2025
Short-List Interviews: Late June – mid July, 2025
Notice of Award: Late July / early August 2025
Negotiate Scope of Work / Fee: August – September 2025
Notice to Proceed: November 1, 2025
Begin Public Input: February 2026